g2 Energy secures prestigious Minety 132kV project

11thDec

g2 Energy were proud to be a part of last weeks Ground Breaking Ceremony on the 132kV Minety Battery Storage project. The project sees two adjacent 50MW developments being built simultaneously – with the site therefore producing 100MWh, making it the largest Battery Storage development in Europe.

We are very excited to be appointed as the Principal Contractor and main BOP Contractor, working with China Huaneng Group! g2 Energy will complete the Contestable Works, working alongside both the DNO SSE, and the appointed INDO to ensure both the Design and Build of the 132kV infrastructure is to the correct specification before adoption. As a part of these works, g2 Energy will build the 132kV SSE compound, and install all associated switchgear and cabling.

 

 

Article written by:

g2admin

Tags:

Posted in: News,